| 1 | Depot |  Plans to extend the line to Antipolo in the province of Rizal were first laid out in 1999 as part of the Metro Manila Urban Transportation Integration Study Master Plan by the Japan International Cooperation Agency. The MMUTIS study endorses the proposed expansion, which includes three stations, one of which was intended for the Vermont Royale Executive Village, but the proposal did not come to fruition. The extension was first approved by the Investment Coordination Committee board of the National Economic and Development Authority in October 2003. On August 3, 2006, the Light Rail Transit Authority announced its intention to extend the line eastward to Antipolo and westward to Port Area, Manila. In May 2011, LRTA secured commitments from the Philippine National Bank, Development Bank of the Philippines, and the Land Bank of the Philippines to fund the extension project. JICA then released a feasibility study report the following October. The extension, starting from the eastern terminus of up to Antipolo station in Antipolo, called for two additional stations: Emerald in Marikina near Sta. Lucia Mall and Robinsons Metro East; and Masinag, in Antipolo near SM City Masinag. The ₱9.7 billion project, at its current form, was approved by the National Economic and Development Authority chaired by then-President Benigno Aquino III on September 4, 2012. The Philippine national government funded the civil works contracts, while JICA funded the contract for the electrical and mechanical systems as part of its Capacity Enhancement of Mass Transit Systems in Metro Manila Project through a ¥43.2-billion loan for various projects of railway lines in Metro Manila. The project aimed to accommodate an additional 80,000 passengers and reduce traffic congestion along Marcos Highway. The lead consultant is a Korean consortium consisting of Foresight Development and Surveying, Soosung Engineering, and Korea Rail Network Authority. The first two packages, awarded to D.M. Consunji Incorporated, covered the design and construction of the viaduct and stations. Unlike the original line which used the pre-casting segmental method of construction, the east extension viaduct made use of AASHTO girders with a deck slab above the girders. Meanwhile, the third package, awarded to Marubeni and DMCI, covered the design and installation of the railway tracks and electrical and mechanical systems of the extension. The project broke ground on June 9, 2015, with an original 2017 deadline. On May 30, 2017, another groundbreaking ceremony was held to mark the start of construction of the two stations. The final phase of construction, covering the installation of the tracks, electrical and mechanical systems, commenced on April 16, 2019. During construction, on March 10, 2017, a truck slammed in a concrete post of the east extension viaduct, killing one and injuring two.
| Package no. | Scope of work | Contractor | Date of award | | 1. | Construction of the viaduct | 
Extension to CogeoPlans for the extension to Cogeo were mentioned in 1992. The Japan International Cooperation Agency has also proposed for a second phase of the east extension to extend the line to Cogeo and downtown Antipolo. There are provisions at the end of the current rail line at Antipolo station for an extension. Two proposals were presented by JICA: a, one-station underground extension, and a, five-station extension, both originating from Antipolo station. As of February 2025, the feasibility study is nearing its conclusion. The extension would have three stations and the alignment is still being finalized.
RouteThe rail line serves the cities that Radial Road 6 passes through: Manila, San Juan, Quezon City, Marikina, Pasig, and Antipolo. The rails are mostly elevated and erected either over or along the roads covered, with sections below ground before and after the station, the only underground station on the line.
StationsThe line serves 13 stations along its -route. The western terminus of the line is the station at Recto Avenue, while the eastern terminus of the line is the station along Marikina–Infanta Highway. Three stations serve as connecting stations between other lines in the metro. is within walking distance to the station of the PNR Metro Commuter Line; is indirectly connected to the station of the same name on the MRT Line 3 through local streets and inter-connected mall passageways inside Araneta City; and is indirectly connected to the station of the LRT Line 1 through a covered walkway. No stations are connected to other rapid transit lines within the paid areas.
| Date opened | Project | Stations | | April 5, 2003 | Phase 1 | – | | April 5, 2004 | Phase 2 | – | | October 29, 2004 | Phase 2 | | | July 5, 2021 | East Extension | – |
OperationsThe line currently runs from 5:00 a.m. PST until 9:30 p.m. on a daily basis. It operates almost every day of the year unless otherwise announced. Special schedules are announced via the PA system at every station and also in newspapers and other mass media. During Holy Week, a public holiday in the Philippines, the rail system is closed for annual maintenance, owing to fewer commuters and traffic around the metro. Normal operation resumes after Easter Sunday. During the Christmas and year-end holidays, the operating hours of the line are modified and shortened, due to the low ridership of the line during the holidays.
Station facilities, amenities, and servicesStation layout and accessibilityStations in the line are located above ground, except for, which is located underground. Stations have a standard layout, with a concourse level and a platform level. The concourse contains ticket booths and is usually below the platform except for the underground station, with stairs, escalators and elevators leading down to the platform level. The levels are separated by fare gates. All stations are barrier-free inside and outside the station, and trains have spaces for passengers using wheelchairs. Most station platforms are long and wide, with some stations having a length of. All stations have side platforms, with the exception of, which as an island platform. Part of the platform at the front of the train is cordoned off for the use of pregnant women, children, elderly, and persons with disabilities. At side-platform stations, passengers are able to switch platforms at the concourse level without leaving the closed system, while passengers can easily switch sides at stations with island platforms. Stations have toilets at the concourse level, both inside and outside the closed system. All Line 2 stations have segregated public restrooms as well as at least one restroom for persons with disability at each station. Folding bicycles are allowed to be brought into trains provided that it does not exceed the LRTA's baggage size limitations of. The last car of each train is also designated as "green zones", where folding bicycle users can ride with their bikes. The line has a total of 72 escalators and 40 elevators across all 13 stations. However, by 2021, only a few elevators and escalators remain operational due to anomalies and corruption involving the procurement contracts, causing complaints from passengers. The elevators and escalators are being repaired and restored since 2022, and more are being repaired and restored as of April 2022.
Shops and servicesStations have at least one stall or stand where people can buy food or drinks, which vary by station. Stations such as Recto, V. Mapa, Gilmore, Araneta Center—Cubao being a primary interchange with MRT-3, Santolan, Marikina—Pasig, and Antipolo are connected to or are near shopping malls and/or other large shopping areas, where commuters are offered more shopping varieties. It is also accessible to major transport terminals in Metro Manila such as Avenida Bus Terminal via Recto and Araneta City Bus Port via Araneta Center—Cubao. Since November 19, 2001, in cooperation with the Philippine Daily Inquirer, passengers have been offered copies of the Inquirer Libre, a free, tabloid-size, Tagalog version of the Inquirer, which is available at all stations.
RidershipThe line is designed and was forecasted to carry 570,000 passengers daily. However, the line operates under its designed capacity since its opening, government officials have admitted that system extensions are overdue, although in the absence of major investment in the system's expansion, LRTA has resorted to experimenting with and/or implementing other solutions to maximize the use of the system, including having bus feeder lines. On October 3, 2014, the line recorded its highest total average of daily passengers, where the ridership within the day reached 281,231 passengers. Before the pandemic, the line had a ridership of 200,000 passengers, but soon decreased in 2019 due to lack of trains and a power trip that closed three stations in October 2019 that was reopened in January 2021. The line served 33,267 passengers daily on average in 2021, with eight trains available for revenue service running at an operating speed of in ten-minute intervals, and one train in reserve for rush hour services, which cuts the time intervals to a minimum of eight minutes. Since 2022, with the return of onsite schooling, ridership has steadily increased, and has returned to pre-COVID-19 pandemic levels on 2025.
Statistics| Year | Daily Average | Yearly Total | | 2003 | 9,221 | 2.36 million | | 2004 | 61,337 | 23.03 million | | 2005 | 116,082 | 41.90 million | | 2006 | 132,154 | 47.57 million | | 2007 | 147,032 | 52.93 million | | 2008 | 161,846 | 58.59 million | | 2009 | 171,996 | 62.09 million | | 2010 | 175,501 | 63.36 million | | 2011 | 176,818 | 63.81 million | | 2012 | 194,268 | 70.33 million | | 2013 | 197,924 | 71.45 million | | 2014 | 201,794 | 72.85 million | | 2015 | 172,318 | 62.21 million | | 2016 | 185,071 | 67.00 million | | 2017 | 182,708 | 65.96 million | | 2018 | 177,260 | 64.70 million | | 2019 | 156,110 | 56.98 million | | 2020 | 45,463 | 12.50 million | | 2021 | 33,267 | 11.84 million | | 2022 | 88,597 | 31.63 million | | 2023 | 138,455 | 49.42 million | | 2024 | 147,618 | 53.29 million | | 2025 | 162,742 | 58.75 million |
Rolling stockThe line runs sixteen electric multiple units made in South Korea by Hyundai Rotem powered by Toshiba-made VVVF inverters. The trains came in together with the fourth package during the system's construction. The four-car trains have a capacity of 1,628 passengers, which is more than the normal capacity of the rolling stock of Lines 1 and 3. The trains are capable of running at a maximum design speed of, but only run at a maximum operational speed of. These trains prominently use wrap advertising. In 2017, the entire train fleet was retrofitted with the TUBE, a passenger information system powered by LCD screens installed near the ceiling of the train that shows news, advertisements, current train location, arrivals and station layouts. In 2019, the train ventilation was upgraded to replace the aging air-conditioning units and to alleviate complaints of the commuters for uncomfortable hot rides. Two years later, three train sets underwent refurbishment and resulted in new fitted propulsion systems and train monitoring systems from Woojin Industrial Systems. The LRTA is also acquiring 14 additional train sets by 2020 to augment the existing 18 sets, due to the expected increase of passengers ahead of the East Extension, and the West Extension. The purchase however was delayed to 2022. No updates were made as of 2024. Included in the design-and-build contract of the west extension is the procurement of five four-car train sets.
DepotThe line maintains an at-grade depot in Barangay Santolan in Pasig, near Santolan station in the side of Barangay Calumpang in Marikina. The depot occupies approximately of space and serves as the headquarters for light and heavy maintenance. Due to its location in a flood-prone area, the depot was raised above ground level. It is connected to the mainline network by a spur line. The depot is capable of storing 24 sets of electric multiple units, with the option to expand to include more vehicles as demand arises. They are parked on several sets of tracks, which converge onto the spur route and later on to the main network. There are eight decommissioned 1000 class and one set of 1100 class trains formerly used in LRT Line 1 being stored in this depot due to the non-availability of stabling tracks to store the new 13000 class trains at the Line 1 depot in Parañaque.
Other infrastructureSignalingThe line uses a fixed block system with automatic train control, which has three subsystems: automatic train protection, automatic train operation, and Rail9000 automatic train supervision. The ATO subsystem automatically drives the trains, while the opening and closing of doors is controlled by an onboard train attendant. The ATP system, meanwhile, maintains safe operations and monitors the train's speed. Lastly, the Rail9000 ATS system is located at the operations control center at the line's Santolan Depot, which directs train operations and monitors the train movement along the line. Other components of the signaling system includes train detection through track circuits and Westrace MK1 computer-based interlocking. The signaling equipment were manufactured by Westinghouse Signals. The signaling system was upgraded with the replacement of its communication link and the upgrading of the Westrace interlocking module. The project started on February 15, 2022, and was completed on March 29.
TracksThe rails are rails designed to the UIC 54 rail profile. The rails are supported by concrete plinths.
Plans and proposalsWest extensionA extension of the line to the Manila North Harbor in Tondo has been proposed. It was first announced in August 2006, when the LRTA announced the then-proposed east and west extensions, and was approved by the National Economic and Development Authority on May 19, 2015. The construction of this extension would create three stations, one near the [Tutuban station|Tutuban PNR station], one in Divisoria, and one near the North Port Passenger Terminal in Manila North Harbor's Pier 4 which would serve as its terminus. In an interview, LRTA Administrator Ret. Gen. Reynaldo Berroya stated that they are aiming to finish the project by 2022 to 2023. The project is now expected to start construction in 2025. The total project cost is estimated to be ₱10.12 billion. In 2019, WESTRAX Joint Venture was awarded the contract for the consultancy services for the project. In October 2019, the project was under bidding process, consisting 3 stations,,, and, with the project scheduled to be completed by 2024. On August 27, 2020, the Light Rail Transit Authority published the bidding documents for the design-and-build contract for the west extension. According to the documents, the turn back area after the station will have three tracks; two of which are the main tracks and one serves as a pocket track. The three stations will feature side platforms. The project was originally planned to be funded through a public-private partnership scheme, in line with the Marcos administration's policy to use the said scheme to complete various infrastructure projects. The contract would have also covered the procurement of five new four-car trains, along with the maintenance of the line and the refurbishment of the trains. However, it was decided that the government will instead fund the project through the national budget. In January 2025, LRTA stated that the process of right of way acquisition for the West Extension is now underway.
PrivatizationThe privatization of the operations and maintenance of Line 2 was planned by the then-Department of Transportation and Communications as part of the agency's improvement and modernization of the railway lines in the Philippines. The bidding process for this project begun on September 13, 2014. In this project, the interested companies were required to submit pre-qualification documents and submit a bid proposal if the company is qualified for the bidding. In January 2015, four companies submitted pre-qualification documents for the project. The bidders included Aboitiz Equity Ventures with SMRT Transport Solutions, DMCI Holdings with Tokyo Metro, Light Rail Manila 2 Consortium, and San Miguel Corporation with Korea Railroad Corporation. All bidders were pre-qualified for the bidding. However, the project would eventually be shelved in 2016. In 2017, it was reported that the Metro Pacific Investments Corporation was interested in a possible auction for the privatization of the line. The plan to privatize the operations and maintenance of the line was restarted in October 2019, following a power trip that damaged two rectifiers. Since then, no new reports have surfaced about this plan as of 2021.
Capacity expansion and upgradeDue to the aging of the line, a capacity expansion project for the line was announced in April 2022. The project would include upgrades to the trains, signaling, telecommunications, power supply, overhead systems, railway tracks, and other system equipment. The project is still under the stages of the procurement of a consultant for the project, which would assess the current condition of the line. TÜV Rheinland has been shortlisted for the list of consultants and is the only consultant to be shortlisted in June 2022. Like the west extension, the upgrading of the train cars would be funded through a public-private partnership scheme. The contract would also cover the maintenance of the line and the construction of the west extension.
Incidents- On July 12, 2006, at 7:30 AM, lightning struck the power cables near the Santolan station, interrupting train operations.
- On August 15, 2006, at 8:45 AM, lightning struck the power cables, which is the second incident reported in a month. Normal operations were restored before 12:00 noon.
- On May 20, 2008, at 6:45 PM, lightning struck the line's power supply, interrupting operations.
- On July 23, 2008, a power interruption disrupted the line operations, leaving the Santolan-Cubao section only operational.
- On June 11, 2011, a man was severely injured after jumping in front of a moving train at the Araneta Center–Cubao station. This forced the line operations to be suspended.
- On May 9, 2017, at 4:03 PM, a tree fell to the tracks at the Anonas area, causing the line's operations to be disrupted and a 2000 class train nearby was hit. The Department of Public Works and Highways local office was doing roadworks at the site of the incident when they accidentally hit a tree that fell on the tracks. Partial operations between Recto and V. Mapa were implemented, until the line's operations were suspended an hour later. The incident area was cleared and full operations resumed at 7:41 PM.
- On May 30, 2018, a damaged cable between J. Ruiz and V. Mapa stations caused limited operations between Santolan and Araneta Center–Cubao stations at 11:46 AM. Normal operations resumed at 7:46 PM.
- On May 18, 2019, two trains collided between Anonas and Cubao stations, injuring 34 passengers, with none in critical condition. Revenue operations were suspended to give way to maintenance checks, and normal operations resumed at 10:47 AM the next day. Trainset no. 18 returned to service in June 2021, while Trainset no. 13 returned to service in September 2021.
- On October 2, 2019, at 9:43 am, lightning struck the station, causing the power transformers at the and stations to trip and disrupt the power supply. The operations of the line were suspended for safety checks and normal operations resumed at 10:11 AM.
- On October 3, 2019, another power trip caused rectifier substations located between Anonas and Katipunan stations and in the Santolan depot to catch fire at around 11 AM, cutting the line's power supply in the area. Line operations from Recto to Santolan were suspended at 11:24 am, and passengers were evacuated from the line with no injuries. The LRTA, MMDA and the Philippine Coast Guard immediately deployed shuttle buses to help ferry stranded passengers. Partial operations between Cubao and Recto stations resumed on October 8, 2019. The initial estimated amount of damages is at around PHP428 million. Santolan, Katipunan and Anonas stations reopened following multiple delays on January 22, 2021.
- On October 8, 2020, a fire broke out in the electrical room at causing the operations to be suspended at 5:10 AM. The fire damaged the station's uninterruptible power supply. Normal operations returned a few hours later.
- On April 7, 2021, the operations of the LRT-2 were halted due to an unspecified "technical problem." Normal operations resumed at 10:50 AM.
- On May 24, 2021, an unspecified technical problem at Santolan station limited the LRT-2 operations between Recto and Araneta Cubao stations. Full operations resumed the following day.
- On June 17, 2021, a technical problem at the line's control center halted the LRT-2 operations. Normal operations resumed at 4:59pm.
- On August 16, 2021, operations were suspended between Cubao and Santolan due to an unspecified technical problem. Operations resumed at 4:20pm. -->
- On September 17, 2021, a defective catenary wire at the east extension area caused disruptions in operations. A shuttle service between Santolan and Antipolo was implemented at 9:43 AM. On the same day, the line's operations were briefly suspended at 11:36 AM after a tangled t-shirt was seen hanging at the contact wires between Cubao and Anonas stations. Operations with the shuttle service resumed at 11:49 AM, while full end-to-end operations were known to be resumed the following day.
- On October 9, 2021, an entangled balloon was discovered between V. Mapa and Pureza stations, causing the line's operations to be suspended for 30 minutes.
- On November 3, 2021, operations of Line 2 were suspended at 6:00 AM due to a signaling system problem. Operations resumed at 7:57 AM.
- Multiple signaling system problems were reported on November 6, 14, and 25, 2021.
- On July 31, 2022, at 8:00 a.m., operations of Line 2 were limited from Cubao to Antipolo stations due to a broken catenary wire between Legarda and Pureza stations. Full operations resumed the following day at 5:00 a.m.
- On May 14, 2023, at 5:30 AM, operations of Line 2 were limited from V. Mapa to Antipolo stations due to a fire that broke out in the vicinity of Recto station, affecting the power supply and signaling system up to Pureza station. The fire was declared under control at 6:40 AM and line operations returned to normal at 1:15 PM.
- On January 12, 2024, Line 2 operations from Antipolo to Recto was halted by one hour due to technical problems with its power rectifier on the LRT-2 substation. Normal operation service resumed after an hour.
- On August 17, 2024, a street dweller was spotted in between Pureza and Legarda stations. The situation forced to limit services from Antipolo to V. Mapa for a few hours.
- On August 19, 2024, a catenary cable caught fire between Katipunan and Santolan stations. This led the line's operations to be limited from Recto to Cubao until the next morning.
- On September 11, 2024, a power supply problem halted operations between V. Mapa and Recto stations for five hours.
- On September 12, 2024, a damaged pantograph on a 2000 class train at J. Ruiz station caused a brief halt on operations.
- On January 17, 2025, a train broke down, forcing commuters to ride other types of transport. This led to a "half-line" operation from 5:00 AM to 9:00 AM wherein the line would operate from Recto to Araneta Center–Cubao.
- On September 15, 2025, around 11:00pm, a 2000 class train derailed whilst arriving at Santolan station, causing damage to the both train and the tracks which resulted in limited operations between Recto station and Araneta Center–Cubao station until the following day.
|
|